Lake Street Paving Underway
Construction on Lake Street, between Fort Wayne Street and the Fox Farm Road round-about in Warsaw, began this morning and will continue through at least Tuesday.
Phase I milling is taking place today with the northbound lane of Lake Street. Paving is expected to begin tomorrow, weather permitting. Phase II will involve milling the southbound lane on Monday, July 21, with paving to be completed on Tuesday, July 22, again, weather permitting.
All vehicles should be removed from Lake Street between the hours of 7 a.m. and 7 p.m. during the construction. Any vehicle that is parked on the street and interferes with milling or paving will be towed. Parking will be allowed after construction has been completed or after 7 p.m. each night.